Start with the plot and the contracting party
Ask for the precise identification of the land, the seller’s details and confirmation of whether the seller owns it. The brand in the advertisement may differ from the company signing the contract. Establish who is responsible for construction and who must refund money or remedy defects.
In the area controlled by the Republic of Cyprus, the DLS describes protection associated with depositing a sale contract and the requirement for an up-to-date encumbrance certificate for contracts covered by the new rules. Your lawyer should explain how these provisions apply to the project. In the north, disputed land rights require separate investigation; a local contract does not remove this issue.
Distinguish issued permits from plans
Ask for permits covering the phase containing the unit you are buying. A document for a neighbouring building or the general development is not enough. Have the plans checked against the apartment number, floor, parking space, terrace and layout specified in the contract.
Ask which communal facilities will be built alongside your building and which will follow later. A pool shown in a render may belong to another phase. You need to know whether completing it is an obligation owed to you, the applicable deadline and the remedy for non-completion. Any clause allowing design changes needs careful discussion.
Turn “high specification” into a specification
List the materials, windows and doors, insulation, air conditioning, kitchen and bathroom fittings and installation provisions. For each item, agree technical parameters or an unambiguous description, rather than an inspirational photograph alone. Distinguish equipment included in the price from extras, and connection points from installed appliances.
Check the rules for substituting equivalent materials. Who decides that a replacement is equivalent, and how is quality compared? Ask for the permitted floor-area tolerances and how any changes are accounted for. Items hidden during a presentation matter too: maintenance access, space for equipment, ventilation and terrace drainage.
Link payments to evidence of progress
Compare instalment dates with construction milestones and the documents confirming completion. If an instalment falls due solely on a calendar date, establish what happens if work is delayed. Do not assume you can withhold payment yourself; you need agreed terms and legal advice.
Ask about the completion date, any additional allowance, the procedure for reporting delay and the financial consequences if handover does not happen. Reserve funds for temporary accommodation and maintaining your existing home. A plan based on moving on the advertised completion day is particularly vulnerable to schedule changes.
Check handover and the first years of use
Arrange an independent inspection and a defects report before final settlement. The contract should explain how to report omissions, who remedies them and how repairs are confirmed. Also agree the handover of keys, manuals, warranties, meters and communal-area documentation.
Ask for an operating budget after any introductory developer offer ends. Will costs change when further facilities open? Who pays the share attributable to unsold units? Visit a completed project by the same developer and ask residents about repairs. A completed, occupied building offers a sound basis for comparison, beyond renders and awards.
Keep a dated specification and all agreed changes together. If the seller presents a revised plan, check the differences before accepting it. Trying to reconstruct the agreed standard later from brochures and messages makes it harder to establish what you actually ordered.
This guide is for general information. Ask an independent professional qualified in the relevant jurisdiction to check the property’s circumstances and current legal and tax requirements.